insitu pipe

Our process often achieves significant savings and operational benefits for pipeline companies, because the coating is applied in one continuous pass (per section) from start to finish after the field joints are welded. Companies find lower capital costs and improved coating integrity, reduced timeline when compared to shop coating the line pipe and manually coating the field joints after welding, and improved flow efficiency.

The in situ coating process results in homogeneous coating over weld joints, all bends, pitting, and any weld or minor corrosion defects. The proactively coated lines are less susceptible to corrosion should the inhibitor programme or system fail.

Below is a list of some of our many successful projects from the last decade.

2019

Meota, SK August/September 2019
Insitu cleaned and coated 10kms of 8" new raw water pipeline. International Bar-Rust 236.

Meota, SK July/August 2019
Insitu cleaned and coated 8kms of 8" new raw water pipeline. International Bar-Rust 236.

Saddle Hills, AB August 2019
Insitu cleaned and coated 2.7kms of 8" new pipeline. Highland 74IS.

Fox Creek, AB June 2019
Insitu cleaned and coated 2.4kms of existing 6" oil emulsion pipeline. International Bar-Rust 236.

Saddle Hills, AB February/March 2019
Insitu cleaned and coated 2.9kms of 8” new pipeline. Highland 74IS.

2018

Spirit River, AB November 2018
Insitu cleaned and coated 7.5kms of 8” new pipeline. Highland 74IS.

Spirit River, AB November 2018
Insitu cleaned and coated 7.5kms of 12” new pipeline. Highland 74IS.

Spirit River, AB September 2018
Insitu cleaned and coated 2kms of 6” new pipeline. Highland 74IS.

Myton, Utah May/June 2018
Insitu clean and coat 1.1kms and 1.7kms of 6” existing oil emulsion pipelines. Highland 74IS.

Spirit River, AB January 2018
Insitu cleaned and coated 3.6kms of 10” new water injection line. Highland 74IS.

Meota, SK February 2018
Insitu cleaned and coated 8.7kms of 8” new water injection line. International Bar-Rust 236.

2017

Earring, AB May 2017 Insitu cleaned and coated 2.45 miles of 10” new pipeline. Highland 74IS.

Earring, AB May 2017 Insitu cleaned and coated 0.54 miles of 10” new pipeline. Highland 74IS.

Spirit River, AB April 2017 Insitu cleaned and coated 3.01 miles of 8” new pipeline. Highland 74IS.

Dawson Creek, BC June 2017 Insitu cleaned and coated 1.49 miles of 4” existing produced water pipeline. Highland 74IS.

North Slope, Alaska June/July 2017 Insitu clean and coat 5.6kms of 10” existing oil emulsion pipeline. International Bar-Rust 236

Earring, Alberta October 2017 Insitu clean and coat 15kms of 10” existing oil emulsion pipeline. Highland 74IS.

Fox Creek, AB March 2017 Insitu clean and coat 2.11 miles of 10” existing emulsion pipeline. Highland 74IS.

Valleyview, AB March 2017 Insitu cleaned and coated 1.86 miles of 6” existing pipeline. Highland 74IS.

Spirit River, AB October 2017 Insitu clean and coat 3.8kms of 8” new pipeline. Highland 74IS.

2016

Spirit River, AB, February 2016 Insitu clean and coat 2.36 miles of 8” new pipeline. Highland 74IS.

Spirit River, AB, January 2016 Insitu clean and coat 7.23 miles of 8” new pipeline. Highland 74IS.

Spirit River, AB April 2016 Insitu clean and coat 1.32 miles of 8” new oil effluent pipeline. Highland 74IS.

Joffre, AB, June 2016 Insitu clean 0.93 miles of 4” pipeline.

2015

Dawson Creek, BC July/August 2015 Insitu cleaned and coated 1.39 miles of 3" produced water. International Bar-Rust 236.

Mulligan, AB July 2015 Insitu cleaned and coated 1.82 miles of 6" produced water. Highland 74IS.

Elnora, AB May 2015 Insitu cleaned and coated 1.03 miles of 3" water injection line. Highland 74IS.

Pink Mountain, BC April/May 2015 Insitu cleaned and coated 3kms of 8" water line. International Bar-Rust 236.

Mulligan, AB March 2015 Insitu cleaned and coated 0.75 miles of 4" water disposal line. Highland 74IS.

Mulligan, AB June 2015 Insitu cleaned and coated 1.82 miles of 6" produced emulsion. Highland 74IS.

Mulligan, AB April 2015 Insitu cleaned and coated 1.74 miles of 8" produced emulsion line. Highland 74IS.

Mulligan, AB February 2015 Insitu cleaned and coated 3.10 miles of 8" produced emulsion line. Highland 74IS

Hythe, AB June 2015 Insitu cleaned and coated 0.34 miles of 3" oil line. International Bar-Rust 236.

Earring, AB May 2015 Insitu cleaned and coated 0.96 miles of 8" oil line. Highland 74IS.

Mulligan, AB June 2015 Insitu cleaned and coated 1.82 miles of 6" fuel gas line. Highland 74IS.

Mulligan, AB March 2015 Insitu cleaned and coated 1.74 miles of 6" produced gas pipeline. Highland 74IS.

Grande Prairie, AB November 2015 Insitu cleaned and inhibited 5.59 miles of 8" existing pipeline.

2014

Myton, Utah January 2014 In-situ cleaned and coated 4.26 miles meters of 6" produced water line. International Bar-Rust 236.

Fourth Creek, AB December 2014 Insitu cleaned and coated 1.92 miles of 6" produced water line. Highland 74IS.

Fourth Creek, AB December 2014 Insitu cleaned and coated 1.74 miles of 6" produced water line. Highland 74IS.

Fourth Creek, AB November 2014 Insitu cleaned and coated 5260 meters of 6" produced water line. Highland 74IS.

Hythe, AB May 2014 In-situ cleaned and coated 1.68 miles of 3" water injection line. International Bar-Rust 236.

Hythe, AB May 2014 In-situ cleaned and coated 0.39 miles of 3" water injection line. International Bar-Rust 236.

Spirit River, AB June 2014 In-situ cleaned and coated 1.11 miles of 4" new water injection line. Highland 74IS.

Spirit River, AB April 2014 In-situ cleaned and coated 2.24 miles of 4" new water injection line. Highland 74IS.

Fourth Creek, AB April 2014 In-situ cleaned and coated 2.45 miles of 4" water injection line. Highland 74IS.

Fourth Creek, AB March 2014 In-situ cleaned and coated 2.05 miles of 4" water injection line. Highland 74IS.

Spirit River, AB October 2014 Insitu cleaned and coated 1.42 miles of 4" new water injection line. Highland 74IS.

Brooks, AB August 2014 Insitu cleaned and coated 2.05 miles of 3" oil emulsion line. International Bar-Rust 236.

Brooks, AB August 2014 Insitu cleaned and coated 2.01 miles of 3" oil emulsion line. International Bar-Rust 236.

Brooks, AB August 2014 Insitu cleaned and coated 1.24 miles of 3" oil emulsion line. International Bar-Rust 236.

Brooks, AB August 2014 Insitu cleaned and coated 0.67 miles of 3" oil emulsion line. International Bar-Rust 236.

Fourth Creek, AB December 2014 Insitu cleaned and coated 1.92 miles of 8" produced emulsion line. Highland 74IS.

Fourth Creek, AB December 2014 Insitu cleaned and coated 1.73 miles of 6" produced emulsion line. Highland 74IS.

Fourth Creek, AB November 2014 Insitu cleaned and coated 3.26 miles of 6" produced emulsion line. Highland 74IS.

Ponoka, AB Sept 2014 Insitu cleaned and coated 1.49 miles of 3" oil line. Highland 74IS.

Zama Lake, AB October 2014 Insitu cleaned and coated 1.09 miles of 6" oil line.

Zama Lake, AB Sept 2014 Insitu cleaned and coated 2.57 miles of 3" existing oil line.

Joffre, AB July 2014 In-situ cleaned and coated 0.53 miles of 10" cooling water line within a plant setting. Highland 74IS.

Zama Lake, AB Sept 2014 Insitu cleaned and coated 3.89 miles of 6" existing sour gas line.

Fourth Creek, AB November 2014 Insitu cleaned and coated 3.27 miles of 6" produced gas line. Highland 74IS.

Grande Prairie, AB March 2014 In-situ cleaned and inhibited 2.73 miles of 6" pipeline.

2013

Hythe, AB August/September 2013 In-situ cleaned and coated 0.74 miles of 3" water injection line.

Utah, USA March/April 2013 In-situ cleaned and coated 8.70 miles of 6" water injection line.

Spirit River, AB October/November 2013 In-situ cleaned and coated 5.90 Miles of 4" new carbon steel water injection line.

Ponoka, AB January/February 2013 In-situ cleaned and coated 1.24 miles of 4" CO2 line, 1 km of 6" CO2 line.

2012

Buffalo, AB October 2012 In-situ cleaned and coated 0.93 miles of 4" gas line.

Joffre, AB September 2012 In-situ cleaned and coated 0.77 miles of 8" spent acid line within a plant setting.

Buffalo, AB October 2012 In-situ cleaned and coated 0.93 miles of 4" gas line.

Joffre, AB September 2012 In-situ cleaned and coated 0.77 miles of 8" spent acid line within a plant setting.

2011

Joffre, AB September 2011 In-situ cleaned and coated 0.34 miles of 16" water line within a plant setting.

Joffre, AB August 2011 In-situ cleaned and coated 0.49 miles of 14" water line within a plant setting.

Slave Lake, AB March 2011 In-situ cleaned and coated 0.17 miles of 6" water line.

Winfield, AB October 2011 In-situ cleaned and coated 1.49 miles of 6" oil line.

Winfield, AB September 2011 In-situ cleaned and coated 1.99 miles of 6" oil line.

2010

Joffre, AB April/May 2010 In-situ cleaned and coated 0.49 miles of 8" water line within a plant setting.

Kerrobert, Saskatchewan September/October 2010 In-situ cleaned and coated 1.79 miles of 8" oil line.

Ponoka, AB August/September 2010 In-situ cleaned and coated 1.62 miles of 4" CO2 line.

Ponoka, AB August/September 2010 In-situ cleaned and coated 2.48 miles of 4" CO2 line.

Ponoka, AB August/September 2010 In-situ cleaned and coated 1.60 miles of 4" CO2 line.

Ponoka, AB August/September 2010 In-situ cleaned and coated 0.93 miles of 3" CO2 line.

Ponoka, AB August/September 2010 In-situ cleaned and coated 0.93 miles of 4" CO2 line.

Lodgepole, AB June 2010 In-situ cleaned and coated 0.17 miles of 4" sour gas line.

2009

Winfield, AB Fall 2009 In-situ cleaned and coated 3.16 miles of 8" oil line.

2008

Winfield, AB, Canada Summer/Fall 2008 In-situ cleaned and coated 1.55 miles of 6" oil line.

Winfield, AB, Canada Summer/Fall 2008 In-situ cleaned and coated 1.30 miles of 4" oil line.

Winfield, AB, Canada Summer/Fall 2008 In-situ cleaned and coated 1.12 miles of 4" oil line.

Winfield, AB, Canada Summer/Fall 2008 In-situ cleaned and coated 0.75 miles of 3" oil line.

Winfield, AB, Canada Summer/Fall 2008 In-situ cleaned and coated 0.50 miles 3" oil line.

Joffre, AB, Canada Fall 2008 In-situ cleaned and coated 1.12 miles of 16" cooling water line within a plant setting

2007

Drayton Valley, AB, Canada Fall 2007 In-situ cleaned and coated 0.62 miles of 4" water injection line.